The contractor that botched construction of a $75 million police academy in Baghdad so badly that human waste dripped from the ceilings has produced shoddy work on 13 out of 14 projects reviewed by federal auditors, the top official monitoring Iraq's reconstruction told Congress yesterday.
In a House hearing on what has gone wrong with reconstruction contracts in Iraq, Parsons Corp. quickly became the focus, taking bipartisan heat for its record of falling short on critical projects. The Pasadena, Calif., firm was supposed to build facilities at the heart of the $21 billion U.S.-led reconstruction program, including fire stations, border forts and health-care centers. But inspectors have found a litany of flaws in the firm's work. The one project reviewed by auditors that was being constructed correctly, a prison, was taken away from Parsons before its completion because of escalating costs.
In a report released yesterday, inspectors found that the Baghdad Police College posed a health risk after feces and urine leaked through the ceilings of student barracks. The facility, part of which will need to be demolished, also featured floors that heaved inches off the ground and a room where water dripped so heavily that it was known as "the rain forest."
The academy was intended as a showcase for U.S. efforts to train Iraqi recruits who eventually are expected to take control of the nation's security from the U.S. military. But lawmakers said yesterday they feared it will become a symbol of a different sort.
"This is the lens through which Iraqis will now see America," Rep. Henry Waxman (D-Calif.) said. "Incompetence. Profiteering. Arrogance. And human waste oozing out of ceilings as a result."